What should estimators check before excavation near utilities?

Updated 2026-11-12

Check the plans, specifications and site information for utility locations, owner coordination, location verification and protection requirements. Check who carries each task, what information remains unresolved and how the solicitation requires clarification before pricing.

Check location information and owner coordination

The Occupational Safety and Health Administration provides:

The estimated location of utility installations, such as sewer, telephone, fuel, electric, water lines, or any other underground installations that reasonably may be expected to be encountered during excavation work, shall be determined prior to opening an excavation. [S1]

Check whether the plans identify existing utilities along the excavation route, at crossings and within proposed work areas. Check the drawing legends and utility notes for location qualifications, missing elevations and references to records outside the bid package.

The Occupational Safety and Health Administration also provides:

Utility companies or owners shall be contacted within established or customary local response times, advised of the proposed work, and asked to establish the location of the utility underground installations prior to the start of actual excavation. [S1]

Check exact location and protection scope

The Occupational Safety and Health Administration provides:

When excavation operations approach the estimated location of underground installations, the exact location of the installations shall be determined by safe and acceptable means. [S1]

Check whether the specifications identify required location verification methods, responsible parties and documentation. Check whether the plans identify verification locations and whether the bid schedule addresses that work.

The Occupational Safety and Health Administration also provides:

While the excavation is open, underground installations shall be protected, supported or removed as necessary to safeguard employees. [S1]

Review the excavation package before assigning scope

Check each applicable item below against the plans, specifications, solicitation and supplied site information.

Review itemEstimator check
Utility crossingsCheck whether plan views, profiles and details identify crossing locations, elevations and required clearances.
Verification workCheck whether specifications identify exploratory work, required records and responsibility for restoring verification areas.
Access and sequencingCheck whether the plans and specifications identify equipment access restrictions, work phases and utility coordination milestones.
Service interruptionsCheck whether specifications require outage authorization, temporary service or utility owner attendance.
Payment scopeCheck whether the bid schedule includes separate items for locating, support, relocation and restoration, or directs their inclusion elsewhere.

The Occupational Safety and Health Administration’s Construction eTool provides:

Other unsafe conditions that may be encountered include hazardous atmospheres and electrical hazards from overhead and underground power lines. [S2]

Check the supplied site information and specifications for identified atmospheric hazards, overhead lines and associated planning requirements.

This is general estimating guidance, not engineering, safety or legal advice.

Resolve document discrepancies through the contract

For a federal contract, check whether it includes the Specifications and Drawings for Construction clause. The Federal Acquisition Regulation provides in that clause:

In case of discrepancy in the figures, in the drawings, or in the specifications, the matter shall be promptly submitted to the Contracting Officer, who shall promptly make a determination in writing. [S3]

About this page

Disclosure: Grafton Bidworks publishes this page and makes GBW.

The contractor reviews, decides and sends every bid; GBW does not submit bids to buyers.

Join the waitlist

Questions

What should I check when utility depths are missing?
Check whether profiles, survey records or referenced investigations provide the missing information. Ask the point of contact the solicitation names for questions to clarify required verification work and its payment treatment.
What if a utility owner has not responded?
Check the specifications for the required response procedure and documentation. Ask the point of contact the solicitation names for questions to clarify unresolved coordination requirements before assigning the excavation sequence in the estimate.
Should I include temporary utility support?
Check whether the plans and specifications require temporary support, identify its design responsibility and assign its installation and removal.
What should I check before closing the estimate?
Check whether written clarifications and addenda are reflected in the utility scope, quantities, subcontractor coverage and bid schedule.