What should estimators check before attending or skipping a federal site visit?

Updated 2026-11-15

The Federal Acquisition Regulation’s Site Visit (Construction) provision provides: "Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed." [S1] Check your federal solicitation for attendance requirements, visit arrangements and the Site Investigation and Conditions Affecting the Work clause before deciding whether to attend.

Find the applicable solicitation terms

The Federal Acquisition Regulation’s site visit prescription provides: "The contracting officer shall insert a provision substantially the same as the provision at 52.236-27, Site Visit (Construction), in solicitations which include the clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work." [S2]

This is general estimating guidance, not engineering, safety or legal advice.

Read the inspection acknowledgment before deciding

For a federal contract containing the Site Investigation and Conditions Affecting the Work clause, the Federal Acquisition Regulation provides: "The Contractor also acknowledges that it has satisfied itself as to the character, quality, and quantity of surface and subsurface materials or obstacles to be encountered insofar as this information is reasonably ascertainable from an inspection of the site, including all exploratory work done by the Government, as well as from the drawings and specifications made a part of this contract. Any failure of the Contractor to take the actions described and acknowledged in this paragraph will not relieve the Contractor from responsibility for estimating properly the difficulty and cost of successfully performing the work, or for proceeding to successfully perform the work without additional expense to the Government." [S3]

Use an attendance or nonattendance checklist

Review itemIf attendingIf considering skipping
AccessCheck solicitation instructions for entry credentials, registration and permitted inspection areas.Ask the contracting officer whether another visit arrangement is available under the solicitation.
Transportation and storageCheck the plans for access routes, delivery areas and storage limits to inspect.Check whether the plans identify access routes and storage areas; ask about missing details.
Utilities and ground conditionsCheck the specifications and plans for utility locations and ground conditions to examine.Check the specifications for available utility information and ground investigation records.
Unresolved scopeCheck your plan and specification questions against the solicitation’s question procedure.Ask the contracting officer to clarify unresolved plan and specification requirements before the stated question deadline.

Check physical data and written clarifications

For a federal contract containing the Physical Data clause, the Federal Acquisition Regulation provides: "The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor." [S4]

Check the completed Physical Data clause and referenced specifications for investigation methods, weather records and transportation information.

For a federal solicitation containing the Explanation to Prospective Bidders provision, the Federal Acquisition Regulation provides: "Oral explanations or instructions given before the award of a contract will not be binding." [S5]

Find the solicitation’s written question procedure and deadline. Check whether any explanation affecting your estimate appears in a solicitation amendment.

Locate the differing conditions notice requirements

For a federal contract containing the Differing Site Conditions clause, the Federal Acquisition Regulation provides: "No request by the Contractor for an equitable adjustment to the contract under this clause shall be allowed, unless the Contractor has given the written notice required; provided, that the time prescribed in paragraph (a) of this clause for giving written notice may be extended by the Contracting Officer." [S6]

Find the clause’s notice trigger, timing and recipient in your contract. Check its descriptions of qualifying conditions and its adjustment requirements before making assumptions about later recovery.

About this page

Disclosure: Grafton Bidworks publishes this page and makes GBW.

The contractor reviews, decides and sends every bid; GBW does not submit bids to buyers.

Join the waitlist

Questions

Is attendance mandatory for my bid?
Check your solicitation and amendments for an express attendance requirement; ask the contracting officer to clarify ambiguous wording.
What should I check if I cannot attend?
Check the solicitation’s visit arrangements and inspection language, and ask the contracting officer about access to the site and referenced records.
How should I handle an answer received during the visit?
Check the solicitation’s written clarification procedure and whether the answer appears in an amendment.

Sources